
2013–2014: Early Planning
Conversations about a community recreation path in Conway gained momentum. The Mount Washington Valley Trails Association (MWVTA) began exploring federal and state grant opportunities to fund a multi-use path.
Initial concept: focus on the Bancroft parcel (town-owned land west of Whitaker Woods).
Goal: connect North Conway Village with the Scenic Vista in Intervale via the rail corridor.
Whitaker Woods was not part of the plan at this stage — considered off-limits due to deed restrictions.
2015: Town Meeting Authorization
At the April Town Meeting, Conway voters approved a warrant article allowing the Board of Selectmen to apply for grant funding.
Scope: specifically authorized for the Bancroft alignment, adjacent to and explicitly avoiding Whitaker Woods.
Advocates emphasized that the project would not use tax dollars and would not disturb Whitaker Woods.
MWVTA and the Town promoted the path as both recreational infrastructure and an economic driver.
2016–2018: Continued Efforts
Despite early enthusiasm, grant applications for the Bancroft alignment did not advance.
In 2018, a second Town Meeting article reaffirmed support for pursuing outside funding.
By this point, planning attention shifted toward a southward route: Cranmore to Hemlock Lane.
2019–2021: New Phase 1 — Hemlock to Cranmore
This new project was built largely on state-owned land acquired for the Conway bypass in the 1990s.
The design was straightforward and required few private easements.
With funding secured, Phase 1 broke ground in November 2021.
An additional grant, secured with the help of Governor’s Councilor Joe Kenney, closed a funding gap and allowed the project to be completed.
Although ideas for a Phase 2 extension were beginning to circulate within MWVTA and staff, Whitaker Woods was not presented publicly as part of the project.
2022: Phase 2 EDA Grant Application
Conway town staff, with MWVTA, submitted a successful application to the U.S. Economic Development Administration.
Critical change: the application included a paved alignment through Whitaker Woods.
The alignment submitted with the grant was not vetted with the public.
No town-wide vote was sought to support the Rec Path extension or authorize the new design.
2023–2024: Phase 2 Public Involvement
For the first time, the Whitaker Woods alignment was formally presented to the public.
A public hearing was held in May 2024 — almost two years after grant submission, with a design few had ever seen.
Conservation Commission and BOS meetings revealed concerns over deed restrictions and paving in Whitaker Woods.
Alternate alignments and surface choices were raised but not advanced.
2025: Design Challenges and Alternatives
Regulatory and legal constraints come into greater focus.
NHDES wetlands permitting, use of the NHDOT railroad right-of-way, and deed restriction concerns emerge as major issues.
March 2025: NHDOT denies the submitted 60% design for use of the rail right-of-way.
July 2025: NHDOT offers three alternative concepts (two west side options, one east side).
BOS and public discussions highlight growing tensions over process, transparency, and long-term stewardship.
The path forward remains unresolved, with legal, financial, and environmental questions still in play.